Airport closure and reconstruction: What to expect
78-day runway closure scheduled for Spring 2022
JACKSON HOLE, Wyo. – The Jackson Hole Airport will have several large capital projects taking place during the spring of 2021 through the summer of 2022. These projects will allow JAC to operate safely and support airline operations while enhancing the traveler experience. Safety, efficiency, and being good stewards to the environment are our top priority every day and these commitments are considered with every project plan developed for JAC.
Terminal Improvement Projects
The Jackson Hole Airport is our community’s airport, and these terminal projects will help JAC accommodate demands placed on the facility. Many of the projects outlined below increase available space to safely and efficiently conduct airport operations while continuing to meet travelers’ high expectations for customer service and experience.
- Entrance Vestibule/Backflow – May 2021
- Ticketing Counter Expansion – May 2021
- TSA Check Point Remodel – January 19 – June 27, 2022
- Restaurant & Gate Expansion/Remodel – April 11 – November, 2022
- Baggage Claim Marketplace – May 2021 – July 2021
Runway Reconstruction
The lifespan of use for a runway is typically 20 years. The asphalt runway at JAC has been rehabbed four times since it was originally constructed in the late 1970’s and it is due for a total reconstruction in the spring of 2022, which will include a 78-day runway closure from April 11 through June 27, 2022.
According to airport director Jim Elwood, the current runway has reached the end of its life cycle and the Federal Aviation Administration (FAA) recommends replacement of runways every 20-25 years to continue to meet required safety standards.
During the runway reconstruction project, the airport board will have the opportunity to complete several other large projects that will enhance the facility for the community. The Security Screening Checkpoint and Jedediah’s Restaurant, two of the oldest sections of the facility, will be expanded along with the Security Hold Room (where passengers wait for their flights).
The runway reconstruction and additional expansion and remodel projects allow the airport to respond to the immediate needs of the community and stakeholders. These facility improvements are supported by FAA grants, WYDOT grants, airport revenues, and loans. No local or state tax dollars support these projects or the operations at JAC.
This spring, the ticketing lobby will be remodeled to accommodate additional ticket counters and a grab-and-go food concession and dining area will be added within the current baggage claim space.
- Phase I June – October 2021
- Preliminary prep work, paving of runway safety areas, drainage installation and staging of construction materials
- Phase II April 11 – June 28, 2022
- Runway closed for reconstruction
- Phase III July – August 2022
- Runway Grooving and Striping